Posted on August 3rd, 2017 by

Public input is an essential part of the permitting process for energy projects in New Hampshire.  Over the last several years, Granite Staters have had many opportunities to provide state and federal officials with feedback about the Northern Pass proposal, with more opportunities still to come. Comments have been submitted in person and in writing to both the New Hampshire Site Evaluation Committee and the U.S. Department of Energy, agencies charged with reviewing and permitting the project.

Below is a list of public hearings which were held to provide information about the project and give residents an opportunity to meet with Northern Pass experts, as well as let state and federal officials know their thoughts on the project. These hearings are in addition to the written comments submitted to state and federal officials.

 

NHSEC Meeting Summary
Event Name Event Type Date Venue Town County
Public Information Session – Merrimack Pre-Filing (SEC)

*Open House

9/2/2015 Grappone Conference Center Concord Merrimack
Public Information Session – Rockingham Pre-Filing (SEC) *Open House  9/3/2015 Deerfield Fair Pavilion Deerfield Rockingham
Public Information Session – Grafton Pre-Filing (SEC) *Open House 9/8/2015 Mountain Club on Loon Resort Lincoln Grafton
Public Information Session – Coos Pre-Filing (SEC) *Open House 9/9/2015 Mountain View Grand Whitefield Coos
Public Information Session – Belknap Pre-Filing (SEC) *Open House 9/10/2015   Lake Opechee Inn & Spa Laconia Belknap
Public Information Session – Merrimack 45-day Post Filing (SEC) *Open House 1/11/2016 Franklin Opera House Franklin Merrimack
Public Information Session – Rockingham 45-day Post Filing (SEC) *Open House 1/13/2016 Londonderry High School Londonderry Rockingham
Public Information Session – Belknap 45-day Post Filing (SEC) *Open House 1/14/2016 Lake Opechee Inn & Spa Laconia Belknap
Public Information Session – Coos 45-day Post Filing (SEC) *Open House 1/20/2016 Mountain View Grand Whitefield Coos
Public Information Session – Grafton 45-day Post Filing (SEC) *Open House 1/21/2016 Mountain Club on Loon Resort Lincoln Grafton
Public Information Session – Belknap 90-day Post Filing (SEC) 3/1/2016 Mill Falls at the Lake Meredith Belknap
Public Information Session – Coos 90-day Post Filing (SEC) 3/7/2016 Colebrook Elementary School Colebrook Coos
SEC Bus Tour Bus Tour 3/7/2016 Coos (north)
SEC Bus Tour Bus Tour 3/7/2016 Coos (south)
Public Information Session – Merrimack 90-day Post Filing (SEC) 3/10/2016 Grappone Conference Center Concord Merrimack

 

Public Information Session – Grafton 90-day Post Filing (SEC) 3/14/2016 Plymouth State University Holderness Grafton
SEC Bus Tour Bus Tour 3/14/2016 Merrimack
Public Information Session – Rockingham 90-day Post Filing (SEC) 3/16/2016 Deerfield Fair Pavilion Deerfield Rockingham
SEC Bus Tour Bus Tour 3/16/2016 Merrimack (south)

Rockingham

Public Information Session – Coos Additional

Hearing

5/19/2016 Mountain View Grand Whitefield Coos
Public Information Session – Grafton Additional

Hearing

6/23/2016 Plymouth High School Plymouth Grafton
Public Comment Hearing 6/15/2017 49 Donavan St Concord Merrimack
Public Comment Hearing 6/22/2017 49 Donavan St Concord Merrimack
Public Comment Hearing 7/20/2017 49 Donavan St Concord Merrimack
SEC Bus Tour Bus Tour 7/27/2017 Coos
SEC Bus Tour Bus Tour 7/28/2017 Grafton

USDOE Meeting Summary

DOE Public Comment Hearing Scoping Hearing (DOE) 10/6/2015 Grappone Conference Center Concord Merrimack
DOE Public Comment Hearing Scoping Hearing (DOE) 10/7/2015 Mountain View Grand Whitefield Coos
DOE Public Comment Hearing Scoping Hearing (DOE) 10/8/2015 Plymouth State University Holderness Grafton

 

DOE Public Comment Hearing (jointly w/ SEC) Scoping Hearing (DOE 3/7/2016 Colebrook Elementary School Colebrook Coos

 

DOE Public Comment Hearing (jointly w/ SEC) Scoping Hearing (DOE) 3/10/2016 Grappone Conference Center Concord Merrimack

 

DOE Public Comment Hearing Scoping Hearing (DOE) 3/9/2016 Waterville Valley Event Center Waterville Valley Grafton
DOE Public Comment Hearing Scoping Hearing (DOE) 3/11/2016 Mountain View Grand Whitefield Coos

 


Posted on August 3rd, 2017 by

Posted In: SEC, Uncategorized, Updates

Tags: ,


Posted on May 4th, 2016 by

Process continues with more public hearings

The New Hampshire Site Evaluation Committee (SEC) has announced it will hold a public hearing on May 19 at 6 p.m. at the Mountain View Grand Resort, at 101 Mountain View Road in Whitefield to receive public comments on the additional information submitted by Northern Pass to comply with newly adopted SEC rules.

This public hearing is in addition to the five public hearings the SEC held in March. The SEC order, issued on May 4, specifies that the public hearing, including public comments, will be limited to issues presented by the additional information filed by Northern Pass.

The SEC will also hold a hearing on pending motions earlier that day at 11 a.m. at the Mountain View Grand Resort. The hearing will address pending motions on the SEC’s timeframe for reviewing the project and a Northern Pass request for partial waivers under the new SEC rules.

The SEC has held a number of hearings in recent months to address issues related to the adjudicative process – a phase of the SEC’s review which is outlined in state law. A prehearing conference was held on March 22 to address issues relating to interveners, the SEC’s timeframe for reviewing the project, whether to hold additional public hearings, and other procedural issues. On April 12, the SEC held a hearing in Lincoln to discuss pending motions, including all requests to review the SEC’s Order on Petitions to Intervene. On April 22, the SEC issued a temporary procedural schedule beginning the discovery phase of the process.

You can find more information about the hearing on the SEC’s website www.nhsec.nh.gov, or on the Northern Pass website, www.northernpass.us.


Posted on May 4th, 2016 by

Posted In: Meetings, SEC, Uncategorized

Tags: , ,


Posted on March 28th, 2016 by

The New Hampshire Site Evaluation Committee (SEC) issued a Notice and Order on Friday announcing a hearing on April 12 in Lincoln to discuss pending motions on Northern Pass before the SEC.

The SEC is currently reviewing the Northern Pass application as part of the state’s permitting process. This process also includes a number of hearings, such as next month’s hearing on three pending motions. These motions include:

  • All Requests for Review of the Order on Petitions to Intervene under RSA 1 62-H:4, V
  • Applicant’s Request for Partial Waivers Under the Newly Adopted SEC Rules
  • Applicant’s Unassented-To Motion for Protective Order and Confidential Treatment

At the hearing, the Subcommittee will allow parties that filed written motions and/or objections regarding the above matters to supplement their written motions or objections with oral argument, if necessary. After that time, the Subcommittee will consider and deliberate on the pending motions.

The meeting will be held on Tuesday, April 12, 2016, at 10:00 a.m. at the Loon Mountain Resort, 60 Loon Mountain Rd., Lincoln. You can read the SEC’s order online here.


Posted on March 28th, 2016 by

Posted In: Filings, Meetings, Uncategorized, Updates

Tags: , ,


Posted on March 4th, 2016 by

The New Hampshire Site Evaluation Committee (SEC) has issued a notice and order of site inspection to review portions of the Northern Pass route. This site inspection will take place on March 7 and 8 and includes a bus tour along the route, stopping at key points identified in the order.

On March 7, the tour will leave from Colebrook Elementary School to view locations along the route and on March 8, the tour will leave from the Mountain View Grand Resort & Spa to view additional locations. You can learn more about the tour, which is open to the public, by reading the SEC order now posted on our website.

This tour and the public hearings being held this month are part of the state permitting process for Northern Pass. The SEC hosted a public hearing on Northern Pass in Meredith on Tuesday, March 1 and the SEC has four more meetings scheduled to gather public input and comment this month. Two of these meetings will be co-hosted with the U.S. Department of Energy, which is also reviewing Northern Pass as part of the project’s federal permitting process.

For more information about the public hearings and how to participate in the process, go to our Project Journal.

March 7

Coös County

(Co-hosted with DOE)

Colebrook Elementary School

27 Dumont Street

Colebrook, NH

 

March 10

Merrimack County 

(Co-hosted with DOE)

Grappone Conference Center

70 Constitution Avenue

Concord, NH

 

March 14

Grafton County 

Plymouth State University

Welcome Center at the Ice Arena

129 NH Rt – 175A

(Holderness Road)

Holderness, NH

 

March 16

Rockingham County

Deerfield Fair Pavilion

49 Stage Road

Deerfield, NH

 


Posted on March 4th, 2016 by

Posted In: Meetings, Uncategorized

Tags: , , ,


Posted on October 2nd, 2015 by

Concord Info Session

Northern Pass has begun the process of seeking a Certificate of Site and Facility from the New Hampshire Site Evaluation Committee (SEC). This certificate is required before construction can begin on large energy facilities in New Hampshire, such as natural gas pipelines, certain electric power generating plants, and high-voltage transmission lines, including Northern Pass.

Changes were recently made to state law to allow for more public involvement, including adding two members of the public to the SEC. State law also provides a number of opportunities for public comment, including two additional public sessions where New Hampshire residents and other stakeholders can speak about Northern Pass.

Commenting in Writing

The Site Evaluation Committee recently opened a docket for the Northern Pass project, which provides a place for members of the public to submit their written comments. Written comments can be sent by mail, email or fax to the addresses below.

New Hampshire Site Evaluation Committee
Pamela G. Monroe, Administrator
21 South Fruit Street, Suite 10
Concord, NH 03301

Tel. (603) 271-2435
Fax. (603) 271-3878
E-mail: Pamela.Monroe@nh.gov

Members of the public can also file a written comment with the SEC at one of the upcoming Public Information Sessions or joint public hearings (see below).

Commenting in Person

On December 18, 2015, the SEC determined the Northern Pass application is “administratively complete,” starting a year-long series of milestones in the project’s permitting process. Within 45 days of the SEC’s acceptance, Northern Pass must hold another round of Public Information Sessions in each county where the project will be located – Merrimack, Rockingham, Grafton, Coös and Belknap counties. The SEC and other state agencies will also hold at least one joint public hearing on Northern Pass in each of these five counties within 90 days of its acceptance of the application. The public will be able to comment and ask questions at these public sessions.

The dates and locations of the 90-day Public Hearings are listed below. Two of these events – Colebrook and Concord – will be conducted in conjunction with the U.S. Department of Energy (DOE) and will serve as a public hearing for both agencies. The DOE will host two additional meetings on its own during the week of March 7 to take comment on its draft Environmental Impact Statement on the Northern Pass project.

Belknap County

Tuesday, March 1, 5 p.m.
Mill Falls at the Lake
Church Landing
281 Daniel Webster Highway
Meredith

Coös County (co-hosted with DOE)

Monday, March 7, 5 p.m.
Colebrook Elementary School
27 Dumont Street
Colebrook

Merrimack County (co-hosted with DOE)

Thursday, March 10 at 5 p.m.
Grappone Conference Center
70 Constitution Ave
Concord

Grafton County

Monday, March 14 at 5 p.m.
Plymouth State University
Welcome Center at the Ice Arena
129 NH Rt. 175A (Holderness Rd.)
Holderness

Rockingham County

Wednesday, March 16 at 5 p.m.
Deerfield Fair Pavilion
34 Stage Road
Deerfield

Other ways to comment

In addition to the SEC process, Northern Pass is the midst of its federal permitting process. This includes the preparation and review of an Environmental Impact Statement by the U.S. Department of Energy (DOE). The draft EIS, which was issued in July, is a comprehensive study of the potential environmental impact of the project, as well as a number of alternatives routes reviewed by the DOE.

This is a separate process that also includes opportunities for you to comment on the project. Click here if you’d like to learn more about how to submit your comment to the DOE.


Posted on October 2nd, 2015 by

Posted In: Filings

Tags: ,