Posted on September 11th, 2017 by

The New Hampshire Site Evaluation Committee (SEC) will today hear from Terry DeWan and Jessica Kimball of  Terrence J. DeWan & Associates, a landscape architecture and planning firm located in Yarmouth, Maine. Both conducted research and compiled data that was submitted as part of the Northern Pass’ state application, including view simulations along the proposed route. Northern Pass has made the photo simulations of the proposed route available on its website.

Key Points:

  • A visual impact assessment, or VIA, is a systematic analysis of possible changes to the visible landscape resulting from proposed development activity, and the investigation of possible means to avoid, minimize or mitigate the effects of the change
  • The methodology follows a systematic path of inventory, analysis, and determination of effect. It is based upon established criteria developed by federal and state agencies over the past several decades, and is similar to previous work done with regards to transmission lines and other VIA projects
  • Scenic resources are defined as publicly accessible places that have been recognized by local, regional, state, or national authorities for their scenic or recreation quality and are visited by the general public, in part for the use, observation, enjoyment, and appreciation of natural, cultural, or visual qualities. All scenic resources that were identified within the Northern Pass Project Study Area were mapped and added to a database for further evaluation
  • Of the 525 scenic resources identified within three miles of the proposed route, none had overall visual impacts that were characterized as ‘high’, based on the observations and methodology used
  • A significant number of mitigation measures have been incorporated into the planning and design of Northern Pass including:
    • Locating portions of the Project underground to avoid sensitive scenic resources, such as the White Mountain National Forest
    • Using existing road rights-of-way (ROW) for most of the underground sections to minimize the need for new cleared transmission corridors
    • Co-locating the majority of the transmission line in existing transmission corridors to minimize the amount of new corridors
    • Using weathering steel monopole structures in certain areas results in a decrease in color contrasts with the surrounding landscape because they are generally darker in color and have a hue that is more commonly found in the landscape. Monopole structures also have a thinner profile and a simpler appearance than lattice structures
    • Locating new transmission structures in proximity to existing structures in certain locations to maintain the same spacing and avoid irregular linear patterns that can be caused by adjacent conductors being out of synch with each other
    • Matching the materials used for both the relocated 115 kV structures and the proposed transmission structures to minimize contrasts in color and texture and contribute to a sense of visual continuity within the corridor
    • Relocating existing transmission and distribution lines within the existing corridors to provide adequate clearance for the proposed structures and minimize the amount of clearing necessary for their installation
  • Northern Pass as a whole will not be a dominant feature in the landscape. The views from most of the scenic resources already contain evidence of existing human development, often prominently visible from the key observation points
  • Northern Pass will not result in unreasonable adverse effects on aesthetics, to either the six subareas that were identified or to the approximately 900 square-mile Project Study Area as a whole

 


Posted on September 11th, 2017 by

Posted In: Permitting, SEC

Tags:


Posted on September 6th, 2017 by

Draft Record of Decision Addresses Construction of Underground Line Along Existing Roads

The U.S. Forest Service has released its Draft Record of Decision (ROD) recommending that the agency issue a special use permit allowing Northern Pass Transmission to bury approximately eleven miles of transmission lines in areas along existing roads through the White Mountain National Forest (WMNF).  The Draft ROD represents another significant step forward for Northern Pass in the permitting process, and comes on the heels of the Final Environmental Impact Statement released by the U.S. Department of Energy last month – both highlighting the soundness of the proposal and the benefits to New Hampshire and the region.

“This proposed decision by the U.S. Forest Service continues to move Northern Pass forward so that it will have all necessary state and federal permits to begin construction by mid-2018,” Eversource New Hampshire President Bill Quinlan said.  “It is consistent with the key findings of other permitting agencies, including the Department of Energy, the NH Department of Environmental Services and the NH Department of Transportation.”

The Draft ROD is the culmination of seven years of review and extensive public input.  In 2015, Northern Pass announced an improved route that included 52 additional miles of underground to avoid any potential view impacts in and around the WMNF or along the Appalachian Trail.  The Draft ROD supports the project’s conclusion that burial along Interstate 93 is not a reasonable alternative, and states that the improved route “is a reasonable way to transmit electrical power through the WMNF in a minimally impactful way when considering all available alternatives.”

The following excerpts are from the Draft ROD:

  • “I fully understand and acknowledge that there will be short-term, construction-related, impacts to natural and cultural resources on the WMNF, visitors to the area, and private lands/properties located along NH Routes 112 and 116. My decision does not ignore or make light of these effects. I believe the intensity and duration of these effects is more than outweighed by the benefits associated with bringing additional hydropower to the New England grid.” 
  • I believe that the technology is comprehensive, and that the Applicant possesses the ability to effectively construct, operate, and maintain the line underground…Since these alternatives bury the line on the WMNF, instead of the initial proposal for overhead lines, I believe the tradeoffs and environmental impacts to the National Forest and connected areas under Alternatives 4c and 7 are reasonable.”
  • “…the alternatives utilizing I-93 are not consistent with my understanding of NHDOT policies…Therefore, I did not select alternatives that buried the transmission line across the WMNF in the I-93 corridor.

The Forest Service also notes that the project will increase the reliability of New England’s power supply, by reducing reliance on imported natural gas; help to reduce greenhouse gas emissions consistent with public policy goals and the New Hampshire Climate Action Plan; and, provide “meaningful benefits to air quality” in the White Mountain National Forest.

“Meeting long-term energy needs in a sustainable, secure, and cost-effective manner for this region of the country is certainly in the public’s interest,” the Forest Service states.

In the coming weeks, Northern Pass will continue to review the specifics contained in the Draft ROD.

Recent Project Milestones include:

  • The U.S. Department of Energy (DOE) has finalized a Programmatic Agreement (PA) regarding Northern Pass that prescribes the steps necessary to complete the federal and state agency review of historic and archeological resources, including addressing any adverse effects.
  • The U.S. Department of Energy issued the Final Environmental Impact Statement for Northern Pass, concluding that the proposed route is the “preferred alternative,” that the project provides substantial benefits, and will result in only minimal impacts
  • Eversource, the International Brotherhood of Electrical Workers, Quanta Services, Inc., and ABB Inc. finalized a comprehensive Project Labor Agreement
  • The New Hampshire Public Utilities Commission (NH PUC) has approved a request by Northern Pass to cross public waters and public lands
  • The NH PUC determined that Eversource has the legal authority to lease its existing rights-of-way to Northern Pass
  • The NH Site Evaluation Committee (NH SEC) completed the “discovery phase” of the permitting process, which involved nine months of data requests, document production and technical sessions. The final phase of the state permitting process began in April with the commencement of final adjudicative hearings. The hearings are the last step in the state siting process before the NH SEC makes its decision on Northern Pass
  • The New Hampshire Department of Transportation issued its final report to the NH SEC recommending approval of the project
  • The New Hampshire Department of Environmental Services (DES) issued four key approvals of the project, pertaining to the Wetland, Shoreland and Alteration of Terrain permits, and the 401 Water Quality Certificate.  The approvals are essential components of the state siting process being conducted by the NH SEC and, per DES, mark the conclusion of the agency’s review of the project’s siting application

Posted on September 6th, 2017 by

Posted In: Permitting, Uncategorized, Updates