Posted on April 6th, 2017 by

New Hampshire regulators today issued an order that Eversource has made a reasonable showing that it has the right to lease the use of its existing rights of way to Northern Pass. The ruling clears the way for the N.H. Public Utilities Commission to now consider the benefits of the proposed lease agreement between Eversource and Northern Pass.

More than 80 percent of the proposed Northern Pass route is underground or within existing Eversource rights of way. Under the proposed lease agreement, more than 98 percent of the lease revenue received by Eversource will be credited to customers. The NHPUC will now begin to consider the value of the lease and determine whether it is “for the public good.”

Recent Project Milestones

  • The NH SEC completed the “discovery phase” of the permitting process, which involved nine months of data requests, document production and technical sessions.  The final phase of the state permitting process begins with the commencement of final adjudicative hearings on April 13.  The hearings are the last step in the state siting process before the SEC makes its decision on Northern Pass
  • New Hampshire Department of Transportation (NH DOT) issued its final report to the New Hampshire Site Evaluation Committee (NH SEC) recommending approval of the project
  • The New Hampshire Department of Environmental Services (DES) issued four key approvalsof the project, pertaining to the Wetland, Shoreland and Alteration of Terrain permits, and the 401 Water Quality Certificate.  The approvals are essential components of the state siting process being conducted by the SEC, and according to DES, mark the conclusion of the agency’s review of the project’s siting application
  • As part of the permitting process for the Northern Pass transmission project, the NH SEC has held 40 technical sessions– these sessions are an informal opportunity for the parties involved in the Northern Pass state review process to ask and answer questions
  • Northern Pass submitted an updated economic analysisto the NH SEC showing that the project will reduce wholesale energy costs in New England by more than $600 million annually, and eliminate more than 3 million tons of carbon emissions in the region each year
  • Northern Pass secured a key regulatory approvalas ISO New England officially determined that the clean energy project can reliably interconnect with the regional electric grid
  • The New Hampshire Public Utilities Commission granted Northern Pass utility status, determining that the project has the technical, managerial, and financial expertise to operate as a public utility once the project is fully permitted, and that it is in the public good for the project to do so
  • Northern Pass and its contractors completed engineering, or geotechnical, field investigationsalong the underground portions of the proposed project route – a required step in the permitting process to support the progression of a project’s design
  • Northern Pass submitted an advanced designto the NH Department of Transportation for the portions of the project that will be buried under or adjacent to the roadway
  • Northern Pass secured agreements with a highly experienced teamof contractors and material suppliers who will execute the engineering, design and construction of the transmission line
  • The NH SECand the S. Department of Energy held a series of public meetings across New Hampshire to gather feedback as part of their respective permitting processes
  • Business leaders from across the stateannounced their support for Northern Pass in a joint statement to the NH SEC. The diverse group of New Hampshire businesses, including some of the state’s largest employers, urged elected officials to join them as they support the Forward NH Plan, and the “direct economic and unparalleled environmental benefits it will provide to the people and businesses of New Hampshire”
  • The New Hampshire Supreme Court ruled in favor of Northern Pass– confirming that the proposal by Northern Pass to use public highways for underground installation of electric transmission lines is clearly allowed under state law

Posted on April 6th, 2017 by

Posted In: Filings, Uncategorized


Posted on March 2nd, 2017 by

Northern Pass reached another significant milestone yesterday when the New Hampshire Department of Environmental Services (DES) issued four key approvals of the project.  DES’s decisions pertained to the Wetland, Shoreland and Alteration of Terrain permits, and the 401 Water Quality Certificate.  The approvals are essential components of the state siting process being conducted by the NH Site Evaluation Committee (NH SEC), and according to DES, mark the conclusion of the agency’s review of the project’s siting application.  The NH SEC is scheduled to render a final decision on the Northern Pass application later this year.

The approvals from DES follow a series of important milestones and achievements for Northern Pass, which include:

  • As part of the permitting process for the Northern Pass transmission project, the NH SEC has held 40 technical sessions – these sessions are an informal opportunity for the parties involved in the Northern Pass state review process to ask and answer questions
  • Northern Pass submitted an updated economic analysis to the NH SEC showing that the project will reduce wholesale energy costs in New England by more than $600 million annually, and eliminate more than 3 million tons of carbon emissions in the region each year
  • Northern Pass secured a key regulatory approval as ISO New England officially determined that the clean energy project can reliably interconnect with the regional electric grid
  • The New Hampshire Public Utilities Commission granted Northern Pass utility status, determining that the project has the technical, managerial, and financial expertise to operate as a public utility once the project is fully permitted, and that it is in the public good for the project to do so
  • Eversource and Hydro-Québec filed a power purchase agreement (PPA) that ensures Eversource customers in New Hampshire will receive a substantial supply of clean energy from Northern Pass
  • Northern Pass and its contractors completed engineering, or geotechnical, field investigations along the underground portions of the proposed project route – a required step in the permitting process to support the progression of a project’s design
  • Northern Pass submitted an advanced design to the NH Department of Transportation for the portions of the project that will be buried under or adjacent to the roadway
  • Northern Pass secured agreements with a highly experienced team of contractors and material suppliers who will execute the engineering, design and construction of the transmission line
  • The NH SEC and the U.S. Department of Energy held a series of public meetings across New Hampshire to gather feedback as part of their respective permitting processes
  • Business leaders from across the state announced their support for Northern Pass in a joint statement to the NH SEC. The diverse group of New Hampshire businesses, including some of the state’s largest employers, urged elected officials to join them as they support the Forward NH Plan, and the “direct economic and unparalleled environmental benefits it will provide to the people and businesses of New Hampshire”
  • The New Hampshire Supreme Court ruled in favor of Northern Pass – confirming that the proposal by Northern Pass to use public highways for underground installation of electric transmission lines is clearly allowed under state law

Posted on March 2nd, 2017 by

Posted In: Environment, Filings, SEC


Posted on February 15th, 2017 by

An update to the economic analysis of the hydroelectric energy transmitted by Northern Pass shows that the project will reduce wholesale energy costs in New England by more than $600 million annually, and eliminate more than 3 million tons of carbon emissions in the region each year.

The wholesale energy price reductions will ultimately flow to customers as retail energy cost savings. The significant reduction in emissions will help New England states achieve clean air goals.

“…LEI’s modeling update demonstrates that Northern Pass will deliver significant benefits to ratepayers in the form of lower electricity costs, carbon emissions reduction, and a more efficient system…”

(London Economics International Updated Analysis, February 2017)

The study, done by London Economics International (LEI) and filed today with the NH Site Evaluation Committee as part of the project’s ongoing state permitting process, provides an update to a 2015 LEI study that showed similar CO2 emission reductions and average regional economic savings of about $800 million annually.

According to LEI, the change in the estimated annual energy savings since 2015 is due to several factors,  including updated projected natural gas prices, lower forecasted customer energy demand, and a modest net increase in supply during the study period from 2020 – 2030. It also reflects changes to rules governing the Forward Capacity Market (FCM), which is administered by ISO-New England, the region’s electric system operator. The FCM provides incentive payments to energy generators through a competitive process under guidelines set annually by ISO-New England.  These payments are funded by electricity consumers. Although the size of Northern Pass’ impact in terms of megawatts has not changed since 2015, the total amount paid for capacity will be smaller because of ISO-New England’s 2016 FCM rules. As a result, LEI’s updated study now calculates $600 million in annual savings—a number that fluctuates based on annual FCM parameters.

“…this Updated Analysis shows that even in the face of shifting market conditions due to changes in underlying drivers and evolving market rules, a project like Northern Pass will create substantial wholesale electricity market benefits in the form of lower electricity costs, benefiting consumers across New England. In addition, the Updated Analysis suggests that Northern Pass still produces significant reductions in emissions of CO2 within the New England footprint, supporting many states’ legislated greenhouse gas emissions reduction goals and overall societal initiatives to tackle the global Climate Change problem.”

(Testimony of Julia Frayer, Managing Director, London Economics International, February 2017)


Posted on February 15th, 2017 by

Posted In: Filings, SEC


Posted on December 29th, 2016 by

Northern Pass Field Work Highlights: GEOTECHNICAL

drilling-geotech

Throughout 2016, Northern Pass and its contractors conducted engineering, or geotechnical, field investigations along the underground portions of the proposed project route. Geotechnical work is a required step in the permitting process to support the progression of a project’s design. Geotechnical field investigations began in several locations following the completion of a thorough survey of the underground route and the acquisition of required permits.

Work was located in the shoulder, or just off the shoulder, of the roadways of Route 3, Route 112, Route 116, Route 18, and Route 302 and involved a series of drilled holes three inches in diameter, located approximately every 1,000 feet. Holes varied in depth from 15 feet to 65 feet, and core samples were taken at various intervals to document sub-surface conditions. After each hole was complete, they were returned to pre-work conditions in compliance with state permitting requirements. The same process was used at each proposed transition station, converter terminal, and at the Deerfield Substation.

While work was occurring, crews utilized project flaggers and, where necessary, police officers to ensure traffic moved smoothly and safely past project work zones.

Northern Pass Submits Designs and Traffic Control Plans to State

As part of our ongoing permitting process, Northern Pass recently submitted an advanced design to the NH Department of Transportation (NHDOT) for the portions of the project that will be buried under or adjacent to the roadway in the northern section of the proposed route. The design includes a traffic control plan for the underground construction phase of the project to ensure all local traffic will have access to residences and businesses, and that the safety of workers and the traveling public is considered.

Northern Pass is committed to working together with the host communities to minimize potential impact and traveler delay. We have contacted town officials and landowners along the underground route about the traffic control plan and will continue to communicate with them. The project will hold meetings with local officials, business owners, residents and other stakeholders before construction work begins to go over the construction process and expected timeline. Northern Pass will also have a team on the ground to work one-one-one with people along the underground route to individually address the specific needs of each business and resident.

The advanced design and traffic control plan will be reviewed by the NH DOT as part of the permitting process and we anticipate it will be posted on the agency’s website.

NH Manufacturers Warn of the Impact of High Energy Costs

This holiday season, chances are you’ll find some Lindt & Sprungli in your stocking or at your neighbor’s Christmas party. The Swiss chocolate company has a strong New Hampshire connection, operating a plant in Stratham which employs around 1,500 people. But future growth in the state is threatened. The facility pays more than $5 million a year for electricity, a cost the company expects to rise by another half-million in 2017.

“The concerning part for us is that we are at this point, the company is not willing to grow any more in New Hampshire,” said Robert Michalski, vice president of operations at Lindt & Sprungli in a New Hampshire Union Leader article. “The only way that we’re going to be able to grow in New Hampshire further is by finding ways to reduce our energy, our energy costs in this state.”

Source: U.S. Energy Information Administration

Source: U.S. Energy Information Administration

The Union Leader reported there were a number of manufacturing leaders who shared the same concern at the recent NH Business and Industry Association’s 2016 energy symposium in Manchester, including Jeff Chierepko, Sig Sauer’s director of facilities. Sig Sauer employs 1,400 in New Hampshire but opted to build a new 70,000-square-foot plant in Arkansas for its most recent expansion. Arkansas’ energy costs, which are roughly half of that in New Hampshire, were cited as a reason for the decision.

“Our first option was in New Hampshire, but if you look at energy costs and all the other things I mentioned, there’s not even a starting point there,” said Chierepko. “We were pursued by a lot of different states and a lot of them happen to be where energy costs are half. We’d like them all to be in New Hampshire,” he said. “Our energy costs are through the roof.”

The retirement of power plants and New England’s constrained natural gas pipelines during winter months are contributing to high prices. Increasing the supply of diverse sources of new energy to the grid with projects like Northern Pass will help lower energy costs not just for these manufacturers, but for the people who live in New Hampshire as well.

Doing Something about Rates

giunta2

Franklin City Councilor Tony Giunta says he had heard from constituents about the need to do something about New Hampshire’s high energy prices. When businesses can get lower rates in other states, it puts local businesses at a disadvantage, he said. “What I’m saying is, I’m worried,” said Giunta.
He believes lowering costs is important to keeping local businesses here in New Hampshire and can be done through new energy projects like Northern Pass. To hear more of what Giunta said, go to
www.northernpass.us/multimedia.


Posted on December 29th, 2016 by

Posted In: Environment, Filings, ISO New England, Jobs, newsletter


Posted on December 20th, 2016 by

blue-hats

Northern Pass had a landmark year in 2016, reaching a number of milestones key to the project’s approval.  The Department of Energy (DOE) received public comments and held a series of public hearings throughout New Hampshire. At the state level, the NH Site Evaluation Committee (SEC) took comments from the public, held a number of public hearings, and advanced the process through Technical Sessions and decisions on motions.

Looking ahead to 2017, the SEC will hold adjudicative hearings in the spring, and is expected to make a final decision on the project no later than September 30. The DOE is expected to release its final Environmental Impact Statement sometime next year, as well.

Below is a recap of 2016 milestones to highlight how far the project has come this year. We look forward to 2017, with Northern Pass on track to complete all permitting processes.

Permitting

The DOE held public hearings throughout the state in March to gather input on its draft Environmental Impact Statement on Northern Pass.

The SEC held 12 public information sessions and public hearings on Northern Pass throughout the state and in communities along the route from January through June. Northern Pass also organized a series of bus tours of the route for the SEC and interveners in coordination with these hearings.

The discovery phase of the state permitting process began in April, requiring Northern Pass to provide documents to the Counsel for the Public and the interveners to the Northern Pass SEC docket. This process continued into August and concluded with Northern Pass staff providing more than 1,250 data responses.

site-visit1

In the fall, the SEC began its first round of Technical Sessions, which provided an informal opportunity for the parties involved in the Northern Pass state review process to ask questions of project experts. There were 21 session held, covering a wide range of topics related to the project, including construction, project benefits, aesthetics, and economic and environmental impact.

Northern Pass secured a key regulatory approval in July when ISO New England officially determined that the clean energy project can reliably interconnect with the regional electric grid. By approving the project’s I.3.9 application, ISO New England determined Northern Pass will not have a significant, adverse effect on the reliability or operating characteristics of the regional grid and its participants.

The New Hampshire Public Utilities Commission (NHPUC) announced in October that Northern Pass has the technical, managerial, and financial expertise to operate as a public utility once the project is fully permitted, and that it is in the public good for the project to do so. The agreement includes Northern Pass’ commitment to provide $20 million ($2 million a year for 10 years) for programs or initiatives approved by the NHPUC that advance clean energy innovation, community betterment, and economic development in New Hampshire, including energy efficiency programs.

In the Community

Business leaders from across the state representing 50 companies announced their support for Northern Pass in March. In a joint statement to the Site Evaluation Committee, the diverse group of New Hampshire businesses, including some of the state’s largest employers, urged elected officials to join them in support of the project.

NFWF Event Speakers

The National Fish and Wildlife Foundation (NFWF) announced eight conservation, restoration and research grants in August totaling nearly $1 million to restore New Hampshire’s forest and freshwater habitat. The grants were funded through Partners for New Hampshire’s Fish and Wildlife, a partnership between Northern Pass, Eversource and NFWF. Collectively, these projects will open 175 miles of streams for Eastern Brook Trout, improve habitat for New England cottontail, American woodcock, and golden-winged warblers on 852 acres of forestland, and reduce polluted runoff from entering streams, including 47 tons of sediment and 41 tons of phosphorus.

Roger’s Campground in Lancaster unveiled the North Country’s first electric vehicle charging station in May, made possible through funding from Northern Pass and the Forward NH Plan.

In July, Lancaster became the first North Country town to install energy-efficient LED street lights, reducing energy consumption by 60 percent. Switching from conventional to LED street lights was funded by the Forward NH Plan.

LED Streetlight Installation

Emergency responders saw an improvement to their radio communications system in eight communities in northern New Hampshire and Vermont this summer thanks to the installation of a new emergency radio antenna. The antenna, which was funded by Northern Pass, enables police to communicate via radio in areas where radio signal was previously unavailable.

Project Work and Construction

In April, Northern Pass announced the major contractors and material suppliers who will execute the engineering, design and construction of the Northern Pass transmission line once the project receives state and federal permits. Later that month, Northern Pass contractors began field work along the proposed route that continued through the rest of the year. Geotechnical work included soil boring tests along the proposed route to log soil characteristics, and archeological field work included shovel test sampling for historical artifacts, as is required under the National Historic Preservation Act, Section 106 process and by the SEC.

Other Key Decisions

The New Hampshire Superior Court ruled in favor of Northern Pass in May and unequivocally dismissed claims by the Society for the Protection of New Hampshire Forests that use of public highways was subject to the Forest Society’s approval.

In June, Eversource and Hydro-Québec reached a significant agreement that ensures Eversource customers in New Hampshire will receive a substantial supply of clean energy from the Northern Pass hydroelectric transmission project.  The power purchase agreement, or PPA, is expected to deliver additional benefits that, when combined with the lowering of market power prices, bring the total estimated energy cost savings for New Hampshire customers to more than $1 billion.


Posted on December 20th, 2016 by

Posted In: Environment, Filings, ISO New England, SEC


Posted on December 7th, 2016 by

Backfilling a shovel test pit

 

Northern Pass Field Work Highlights: ARCHEOLOGY

Over the last year, Northern Pass contractors conducted archeological field investigations along the Project’s proposed route. Archeological investigations included shovel test sampling for resources in various locations along the existing transmission corridor, and along public roads. The top-most layer, sometimes referred to as the “sod cap”, is removed, and the soil beneath is sifted to search for artifacts.

Once the investigation is completed the soil is backfilled, tamped down, and the top-most layer replaced. This work, which is nearly complete, is required for the National Historic Preservation Act, Section 106 process, and for the NH Site Evaluation Committee (SEC). All findings are considered culturally sensitive and confidential.

NH PUC Grants Northern Pass Utility Status

The New Hampshire Public Utilities Commission (NHPUC) announced recently that Northern Pass has the technical, managerial and financial expertise to operate as a public utility once the project is fully permitted, and that it is in the public good for the project to do so. As a public utility, Northern Pass operations will be subject to the jurisdiction of the NHPUC once the project is in service. This is consistent with how other transmission owners operate in New Hampshire.

“This approval is another milestone for the project, which promises to deliver significant environmental, economic, and energy cost savings to New Hampshire,” said Bill Quinlan of Eversource. “We appreciate the excellent work by the NHPUC staff and Commissioners in evaluating the project, and look forward to further dialogue as the evaluation process continues.”

In addition to granting Northern Pass public utility status, the NHPUC order formalizes Northern Pass’ commitment to provide $20 million ($2 million a year for 10 years) for programs or initiatives approved by the NHPUC that advance clean energy innovation, community betterment, and economic development in New Hampshire, including energy efficiency programs. The funding for these initiatives will come from the Forward NH Fund, which will be established by Northern Pass to provide unique benefits to New Hampshire.

This approval by the NHPUC follows another key regulatory milestone for Northern Pass. In July, Northern Pass was granted an I.3.9 approval by the regional grid operator, ISO New England, which officially determined that the clean energy project can reliably interconnect with the regional electric grid. You can view the NHPUC order on Public Utility Status on the agency’s website.

SEC Wraps UP Northern Pass Technical Sessions

Northern Pass recently completed the Technical Session review phase of the state permitting process. These informal hearings were an opportunity for the parties involved in the Northern Pass state permitting process to ask questions of the project and are part of the New Hampshire Site Evaluation Committee’s (SEC) ongoing review of the project.

The SEC review process will soon move on to Northern Pass’ review of testimony and information provided by experts and witnesses representing the Counsel for the Public and others. For more information about the SEC process, go to the SEC docket on Northern Pass, posted on the agency’s website. You can also find updates about the project and its permitting process on the Northern Pass Project Journal.

apprentice-nh-2

Transmission Project, Job Training Program Puts NH Residents to Work

A joint transmission project between Eversource and National Grid is putting local companies and residents to work in the Merrimack Valley, while the launch of a lineworker certificate program at Manchester Community College is training people for future projects.

A number of New Hampshire-based companies and workers were selected to begin the first phase of construction on the Merrimack Valley Reliability Project (MVRP), a transmission project between Londonderry and Tewksbury, Massachusetts. Local companies include Triple L Trucking and Greymont Trucking of Henniker, M & R Wood Recycling of Derry, A.B. Excavating of Lancaster, U.S. Silt & Site Supply of Bow, Redimix Companies Inc. of Manchester, New England Mat Company of Winchester, and Busby Construction of Atkinson. Members of the International Brotherhood of Electrical Workers (IBEW) Local 104 and other local unions will also provide workers for the project. Non-union workers will also be employed in a variety of roles.

Eversource also announced in October its partnership with Manchester Community College (MCC), the National Electrical Contractors Association, and IBEW Local Unions 104 and 1837 to offer a certification program that will help prepare the next generation of electrical lineworkers in New Hampshire. The partnership offers a limited number of candidates valuable training and the opportunity to progress into Eversource’s paid apprenticeship program.

“This new program fits perfectly into our philosophy of giving students hands-on learning opportunities which lead directly to well-paying jobs in the market,” says Susan Huard, President of Manchester Community College. “This will be an attractive new program for those looking to advance their skills, pursue a new career path with Eversource, or work toward completing a degree.”

For more information about the MCC lineworker certificate program or the Eversource apprenticeship program go to the company website.

van-natta

The Benefits from Northern Pass

New Hampshire resident Michael Van Natta sees a lot of upside when it comes to Northern Pass, like stabilizing energy costs, underground lines reducing potential view impacts, and funding for communities in New Hampshire.

“The benefits package that’s going to communities, if you want to support New Hampshire, you should support it,” said Van Natta. “It’s money coming in to these communities that don’t have a lot of funding.”

To hear more of what Van Natta said, go to the Northern Pass videos page.


Posted on December 7th, 2016 by

Posted In: Filings, Jobs, Uncategorized


Posted on October 17th, 2016 by

The New Hampshire Public Utilities Commission (NHPUC) announced on Friday, October 14 that Northern Pass has the technical, managerial, and financial expertise to operate as a public utility once the project is fully permitted, and that it is in the public good for the project to do so.

As a public utility, Northern Pass operations will be subject to the jurisdiction of the NHPUC once the project is in service.  This is consistent with how other transmission owners operate in New Hampshire.

“This approval is another milestone for the project, which promises to deliver significant environmental and economic benefits, as well as energy cost savings to New Hampshire,” said Bill Quinlan of Eversource.  “We look forward to continuing to move through the state and federal siting processes with the goal of making the benefits of Northern Pass a reality for the state’s energy consumers.”

In addition to granting Northern Pass public utility status, the NHPUC order formalizes Northern Pass’ commitment to provide $20 million ($2 million a year for 10 years) for programs or initiatives approved by the NHPUC that advance clean energy innovation, community betterment, and economic development in New Hampshire, including energy efficiency programs.  The funding for these initiatives will come from the Forward NH Fund, which will be established by Northern Pass to provide unique benefits to New Hampshire.

This approval by the NHPUC follows another key regulatory milestone for Northern Pass.  In July, Northern Pass was granted an I.3.9 permit from the regional grid operator, ISO New England, which officially determined that the clean energy project can safely and reliably interconnect with the regional electric grid.

You can view the NHPUC order on Public Utility Status here.


Posted on October 17th, 2016 by

Posted In: Filings, Press Releases

Tags: ,


Posted on July 21st, 2016 by

Northern Pass has secured a key regulatory approval this week as ISO New England officially determined that the clean energy project can reliably interconnect with the regional electric grid.

By approving the project’s I.3.9 application*, ISO New England determined Northern Pass will not have a significant, adverse effect on the reliability or operating characteristics of the regional grid and its participants.  All energy projects must secure this approval in order to be connected to the New England grid.

Northern Pass is a proposed transmission line that will carry 1,090 megawatts of clean, reliable hydroelectric power to New Hampshire and New England.  The project is currently in the midst of state and federal permitting processes.

 

*In 2014, ISO New England approved the I.3.9 application for the project’s original 1,200 megawatt proposal.

ISO New England I.3.9 Approval 2016

ISO New England I.3.9 Approval 2014


Posted on July 21st, 2016 by

Posted In: Filings, ISO New England


Posted on March 28th, 2016 by

The New Hampshire Site Evaluation Committee (SEC) issued a Notice and Order on Friday announcing a hearing on April 12 in Lincoln to discuss pending motions on Northern Pass before the SEC.

The SEC is currently reviewing the Northern Pass application as part of the state’s permitting process. This process also includes a number of hearings, such as next month’s hearing on three pending motions. These motions include:

  • All Requests for Review of the Order on Petitions to Intervene under RSA 1 62-H:4, V
  • Applicant’s Request for Partial Waivers Under the Newly Adopted SEC Rules
  • Applicant’s Unassented-To Motion for Protective Order and Confidential Treatment

At the hearing, the Subcommittee will allow parties that filed written motions and/or objections regarding the above matters to supplement their written motions or objections with oral argument, if necessary. After that time, the Subcommittee will consider and deliberate on the pending motions.

The meeting will be held on Tuesday, April 12, 2016, at 10:00 a.m. at the Loon Mountain Resort, 60 Loon Mountain Rd., Lincoln. You can read the SEC’s order online here.


Posted on March 28th, 2016 by

Posted In: Filings, Meetings, Uncategorized, Updates

Tags: , ,


Posted on December 22nd, 2015 by

Five hearings provide an opportunity for residents to participate in the State permitting process

Today the New Hampshire Site Evaluation Committee (SEC) scheduled a series of five Public Information Sessions. The Public Information Sessions are another step forward for Northern Pass as it makes its way through the state review process.

The locations, dates and times of these sessions are listed in an order and notice issued by the SEC, as well as a separate procedural order. Under state law, Public Information Sessions must be held in each county in which the proposed facility is to be located within 45 days of a project’s application being accepted. Similar to the Public Information Sessions held in September, they give residents another opportunity to participate in the state approval process.

“The purpose of the public information session is to provide the public with information on the proposed Project, to provide an opportunity for comments and questions from the public, and to explain the process the Subcommittee will follow in reviewing the application,” states the public notice issued by the SEC today.

Before and during the Public Information Sessions, Northern Pass will also host an Open House for residents who wish to learn more about the project and meet with project representatives one-on-one. Open Houses will begin at 5 p.m. at each of the venues listed below.

Merrimack County: January 11, 2016 at 6 p.m., Franklin Opera House, 316 Central Street, Franklin, NH

Rockingham County: January 13, 2016 at 6 p.m., Londonderry High School, 295 Mammoth Road, Londonderry, NH

Belknap County: January 14, 2016 at 6 p.m., Lake Opechee Inn and Spa, 62 Doris Ray Court, Laconia, NH

Coös County: January 20, 2016 at 6 p.m., Mountain View Grand Resort & Spa, 101 Mountain View Road, Whitefield, NH

Grafton County: January 21, 2016 at 6 p.m., The Mountain Club on Loon Resort and Spa, 90 Loon Mountain Road, Lincoln, NH


Posted on December 22nd, 2015 by

Posted In: Community, Filings, Meetings, Updates


Next Page »