Posted on October 5th, 2017 by

The final witnesses for Northern Pass completed their testimony before the New Hampshire Site Evaluation Committee (SEC) on Monday, marking the conclusion of Northern Pass’ witness presentation before the SEC. Northern Pass presented 25 witnesses over 43 hearing days, describing in detail the following aspects of the project.

Forward NH, Project Route, Clean Energy RFP         Financial 

Public Health & Safety                                                             System Reliability         

Construction                                                                                  Environmental               

Tourism                                                                                             Property Taxes                

Property Values                                                                           Historical/Archeological 

Aesthetics                                                                                       Orderly Development                                                            

The SEC also heard from members of the International Brotherhood of Electrical Workers (IBEW) last week, who testified about the job opportunities available for New Hampshire workers, as well as Allen Bouthillier, Lancaster business owner and member of the Coös County Business and Employers Group, who spoke about the economic opportunities Northern Pass will bring to the North Country.

The Counsel for the Public and intervenors are set to begin presenting their witness testimony later this week.

Other Recent Project Milestones include:

  • The U.S. Forest Service has released its Draft Record of Decision (ROD) recommending that the agency issue a special use permit allowing Northern Pass Transmission to bury approximately eleven miles of transmission lines in areas along existing roads through the White Mountain National Forest (WMNF).
  • The U.S. Department of Energy (DOE) has finalized a Programmatic Agreement (PA) regarding Northern Pass that prescribes the steps necessary to complete the federal and state agency review of historic and archeological resources, including addressing any adverse effects.
  • The U.S. Department of Energy issued the Final Environmental Impact Statement for Northern Pass, concluding that the proposed route is the “preferred alternative,” that the project provides substantial benefits, and will result in only minimal impacts
  • Eversource, the International Brotherhood of Electrical Workers, Quanta Services, Inc., and ABB Inc. finalized a comprehensive Project Labor Agreement
  • The New Hampshire Public Utilities Commission (NH PUC) has approved a request by Northern Pass to cross public waters and public lands
  • The NH PUC determined that Eversource has the legal authority to lease its existing rights-of-way to Northern Pass
  • The New Hampshire Department of Transportation issued its final report to the NH SEC saying it will issue a permit for the project
  • The New Hampshire Department of Environmental Services (DES) issued four key approvals of the project, pertaining to the Wetland, Shoreland and Alteration of Terrain permits, and the 401 Water Quality Certificate.  The approvals are essential components of the state siting process being conducted by the NH SEC and, per DES, mark the conclusion of the agency’s review of the project’s siting application

Posted on October 5th, 2017 by

Posted In: SEC, Updates