The NH Site Evaluation Committee today voted to extend the deadline for their final written decision on Northern Pass by six months, to March 31, 2018.

Northern Pass is disappointed in today’s decision considering this review process was already extended by nine months, from what was originally a 12-month process under recently enacted NH law.

We’re encouraged by the SEC’s willingness to pursue options for concluding the review in advance of the new deadline.

We remain confident in our ability to achieve a 2020 in-service date.  Further, we are convinced that we have submitted the most mature project into the Massachusetts Clean Energy RFP and we continue to believe that we will be in a position to start construction in the second quarter of 2018.