The U.S. Department of Energy (DOE) has finalized a Programmatic Agreement (PA) regarding Northern Pass, which marks further progress in the federal permitting process for the clean energy project.  The PA is a legally binding agreement that prescribes the steps necessary to complete the federal and state agency review of historic and archeological resources, including addressing any adverse effects.  The PA is part of a larger process under Section 106 of the National Historic Preservation Act, and is separate from the National Environmental Protection Act (NEPA) environmental review.

The signatories to the PA include officials from DOE, the U.S. Forest Service, the U.S. Department of Interior, the New Hampshire Division of Historical Resources, and Northern Pass Transmission.

Recent Project Milestones include:

  • The U.S. Department of Energy issued the Final Environmental Impact Statement for Northern Pass, concluding that the proposed route is the “preferred alternative,” that the project provides substantial benefits, and will result in only minimal impacts
  • Eversource, the International Brotherhood of Electrical Workers, Quanta Services, Inc., and ABB Inc. finalized a comprehensive Project Labor Agreement
  • The New Hampshire Public Utilities Commission (NH PUC) has approved a request by Northern Pass to cross public waters and public lands
  • The NH PUC determined that Eversource has the legal authority to lease its existing rights-of-way to Northern Pass
  • The NH Site Evaluation Committee (NH SEC) completed the “discovery phase” of the permitting process, which involved nine months of data requests, document production and technical sessions. The final phase of the state permitting process began in April with the commencement of final adjudicative hearings. The hearings are the last step in the state siting process before the NH SEC makes its decision on Northern Pass
  • The New Hampshire Department of Transportation issued its final report to the NH SEC recommending approval of the project
  • The New Hampshire Department of Environmental Services (DES) issued four key approvals of the project, pertaining to the Wetland, Shoreland and Alteration of Terrain permits, and the 401 Water Quality Certificate.  The approvals are essential components of the state siting process being conducted by the NH SEC and, per DES, mark the conclusion of the agency’s review of the project’s siting application