In this video, Tom True, senior project manager for Coler & Colantonio, discusses the process of gathering environmental data for The Northern Pass project. This is done only after permission is received from landowners along the proposed route of the new transmission line. The data differs depending on the season, so three or four visits to a property may be required over the course of a year or two.

Respect for property owners’ privacy is of the utmost concern. Owners are notified two to three weeks in advance of a visit, and those gathering the data take care to leave the property in a safe and respectful condition. Additionally, by granting the right to gather data, property owners do not give up any other property rights—the right of access is to gather data only.